Exterior of the Viet Y Steel Plant in Hai Phong.
A Technically and Constructionally “Heavy” Project
The plant is built on an area of 3 hectares, including various components such as the main workshop, auxiliary areas, landscape infrastructure, and particularly the connection area between the old and new workshops. The overall structure is a perfect combination of solid reinforced concrete foundations and prefabricated steel frames up to 20 meters high, with three steel frame systems spanning approximately 28 meters each, using a total steel structure weight of 5,000 tons.
The steel frame structure with a span of 28 meters has been constructed to align with the operational design of the plant.
Precision to Every Millimeter – Foundation for High-Tech Production Lines
As an industrial project integrating the most modern equipment, 100% imported from the world's leading steel group Danieli (Italy), the Viet Y Steel Plant project sets special requirements for precision in construction – particularly in machine foundation components and equipment installation positions.
The modern conveyor belt system has been integrated into the foundation of the project's machinery.
The production line system is installed and anchored to the reinforced concrete machine foundations via pre-installed technological bolt holes.
Additionally, the technical connection between the old and expanded workshops has been synchronously implemented by Coteccons, ensuring seamless production lines operate accurately without errors during operation.
The old workshop and the expanded workshop were seamlessly connected, enabling the production line to successfully conduct trial operations and produce the "first steel product”.
Elevated platform system enabling access and monitoring of plant operations from above.
Besides complex technical solutions and high completion accuracy, Coteccons also focuses on solutions to optimize costs and protect the environment. The natural lighting system on the roof, skylights, and louvers around the workshop walls not only minimize energy consumption but also create a spacious working environment, contributing to a sustainable and economical industrial space.
Natural lighting and ventilation system optimizing operational costs, aiming for sustainable industrial space.
On-Time Handover – Affirming the Reputation and Overall Capability of Vietnam's Top Contractor
The project was handed over on schedule after 14 months of construction, enabling the Viet Y Steel Plant to enter the operational phase as planned in May 2025. With a steel rolling capacity of 500,000 tons/year and a billet production line of 552,000 tons/year, the plant will significantly contribute to the development of Vietnam's steel industry – providing high-quality, stable products for both domestic and international markets.
Where high-quality steel products are produced, serving the domestic and international industry.